Construction Milestones

We are working to provide the facilities our students need to succeed in the 21st century. Follow milestones in our progress.

Roof work on Klahowya Grandstands
Capital Projects Update: January 2020
01/23/2020
We've completed secure entryway construction at all schools and more!
Read More About Capital Projects Update: January 2020
clear
Counter tops going in Ccottonwood Elementary's new entrance
Capital Projects Update: November 2019
11/26/2019
With major bond projects wrapping up, we’re focusing more attention on our promises to make critical repairs at all schools.
Read More About Capital Projects Update: November 2019
clear
Ribbon cutting at new CKHS
Capital Projects Update: October 2019
10/17/2019
Earlier this month we celebrated completion of the biggest and final large construction project funded by the 2016 bond. But we’re not done yet!
Read More About Capital Projects Update: October 2019
clear
Cougar Valley Entrance
More Secure School Year Begins
09/25/2019
Walk into the entrance of any Central Kitsap school this year, and you’ll see a promise kept.
Read More About More Secure School Year Begins
clear
Entrance to new CKHS
Capital Projects Update: September 2019
09/19/2019
We opened the year with the newly built Central Kitsap High. All three high schools celebrated home football games, with fans in grandstands.
Read More About Capital Projects Update: September 2019
clear
Security work at Cottonwood
Capital Projects Update: June 2019
06/24/2019
This summer, we’ll wrap up work at CK High and on security improvements at most of our schools and more!
Read More About Capital Projects Update: June 2019
clear
CKHS new gym
Capital Projects Update: May 2019
05/24/2019
Classes are in session at CK Middle, and work at CK High is progressing quickly.
Read More About Capital Projects Update: May 2019
clear
CKHS new gym
Capital Projects Update: April 2019
04/29/2019
Classes are in session at CK Middle, and work at CK High is progressing quickly.
Read More About Capital Projects Update: April 2019
clear
Students and staff cut the ribbon
New CKMS Is Now Open!
04/10/2019
It's official! Our rebuilt CKMS is open!
Read More About New CKMS Is Now Open!
clear
ckms studnets in new common areas
Capital Projects Update: March 2019
03/29/2019
We’ve reached a major milestone with the completion of Central Kitsap Middle School!
Read More About Capital Projects Update: March 2019
clear
CKMS classroom with desks
Capital Projects Update: February 2019
02/27/2019
Most major construction work at Central Kitsap Middle School is complete!
Read More About Capital Projects Update: February 2019
clear
PineCrest secure entrance construction
Capital Projects Update: January 2019
01/29/2019
Next month, work will be going on at half our schools!
Read More About Capital Projects Update: January 2019
clear
Staff gathered on stage to cut the ribbon.
Thank You from OHS!
01/28/2019
Thank you to all who joined us to cut the ribbon on our modernization and addition project!
Read More About Thank You from OHS!
clear
Demolition at Woodlands
Security Construction Starts at Four More Schools
12/10/2018
We’re reconfiguring main entrances to allow our staff to have eyes on all visitors before we grant access to a school.
Read More About Security Construction Starts at Four More Schools
clear
This is the image for the news article titled Capital Projects Update: November 2018
Capital Projects Update: November 2018
11/26/2018
It's been a busy fall! Next month, we'll welcome students into Silverdale's new wing.
Read More About Capital Projects Update: November 2018
clear
This is the image for the news article titled Capital Projects Update: October 2018
Capital Projects Update: October 2018
10/17/2018
We're making a lot of progress toward completing big projects this school year!
Read More About Capital Projects Update: October 2018
clear
This is the image for the news article titled Ribbon Cutting Marks Opening of the Klahowya Addition
clear
Ribbon cutting at Klahowya
Capital Projects Update: September 2018
09/20/2018
We've celebrated the first of several milestones this school year
Read More About Capital Projects Update: September 2018
clear
Flooring in the new auxiliary gym
Capital Projects Update: June 2018
06/21/2018
We’ve accomplished a lot this school year, and we’re gearing up for even more work this summer.
Read More About Capital Projects Update: June 2018
clear
Seniors got a sneak peek at the new core in June.
Significant Portion of OHS Addition Opens this Fall
06/20/2018
Olympic High School’s new core will open in two phases beginning this fall.
Read More About Significant Portion of OHS Addition Opens this Fall
clear
CK Schools will add a left-turn lane on Anderson Hill Road near the new CKMS entrance
Summer Road Work Will Impact Anderson Hill
06/18/2018
CK Schools begins road improvements to improve access to the new CK High & Middle.
Read More About Summer Road Work Will Impact Anderson Hill
clear
Future seating area along the OHS commons.
Capital Projects Update: May 2018
05/29/2018
Exterior studs and coverings are going up as construction work progresses on the insides of our major building projects
Read More About Capital Projects Update: May 2018
clear
Future seating area along the OHS commons.
Capital Projects Update: April 2018
04/25/2018
Exterior studs and coverings are going up as construction work progresses on the insides of our major building projects
Read More About Capital Projects Update: April 2018
clear
CK Campus from above.
Capital Projects Update: March 2018
03/15/2018
A major phase of our work to secure access to schools begins.
Read More About Capital Projects Update: March 2018
clear
This is the image for the news article titled Secure Entrances Under Construction
clear
CK High steel beams
January 2018 Update
01/25/2018
Two campuses reach major milestones as steel arrives.
Read More About January 2018 Update
clear
Inside the Annual Report
Annual Report Out in Mailboxes
12/18/2017
It's been a busy year improving facilities for our students!
Read More About Annual Report Out in Mailboxes
clear
Wall near future entrance
Capital Projects Update: December 2017
12/14/2017
New walls are now visible at all three of our school construction sites!
Read More About Capital Projects Update: December 2017
clear
New Service Building Hosts Grand Opening
New Service Building Hosts Grand Opening
12/08/2017
Completion of this building fulfills the last major project promised to our community with the 2011 capital projects measure.
Read More About New Service Building Hosts Grand Opening
clear
Designed for Learning Infographic
Designed for Learning
10/25/2017
School and classroom design can impact student achievement.
Read More About Designed for Learning
clear
Olympic High School
Capital Projects Update: October 2017
10/11/2017
We're making progress on our major school construction projects.
Read More About Capital Projects Update: October 2017
clear
Alissa Capuano stands in front of Olympic High as its demolished.
Oly Grad Returns to School
09/20/2017
Alissa Capuano helped in the demolition and preparation work to rebuild the OHS core.
Read More About Oly Grad Returns to School
clear
Shovels turn for the groundbreaking.
Celebrating a New Start for CK High and Middle
09/08/2017
Students, staff and community celebrated the start of construction on campus.
Read More About Celebrating a New Start for CK High and Middle
clear
This is the image for the news article titled Klahowya's New Turf Field
Klahowya's New Turf Field
08/31/2017
This month marked the beginning of a new era for Klahowya athletics.
Read More About Klahowya's New Turf Field
clear
An excavator pulls down the Olympic High School sign
Crews Demolish Center of Olympic High
07/25/2017
The work on the middle portion will make way for a two-story replacement.
Read More About Crews Demolish Center of Olympic High
clear
Students and staff turn shovels near the OHS entrance.
Shovels Turn for Olympic Modernization
06/01/2017
Students, staff and dignitaries officially break ground.
Read More About Shovels Turn for Olympic Modernization
clear
School and district dignitaries turn shovels of dirt.
Ceremonial Shovels Turn at Klahowya
04/17/2017
Construction starts on the Klahowya addition project.
Read More About Ceremonial Shovels Turn at Klahowya
clear
This is the image for the news article titled Work at Olympic High Starts in Spring
Work at Olympic High Starts in Spring
02/10/2017
A major milestone clears the way for construction document preparation.
Read More About Work at Olympic High Starts in Spring
clear
This is the image for the news article titled Annual Report Headed to Mailboxes
Annual Report Headed to Mailboxes
02/06/2017
Get a summary of our past year's Capital Projects accomplishments.
Read More About Annual Report Headed to Mailboxes
clear
This is the image for the news article titled Board Approves Updated CK Campus Floor Plan
Board Approves Updated CK Campus Floor Plan
01/19/2017
As part of the design process, a revised floor plan design was presented to the board.
Read More About Board Approves Updated CK Campus Floor Plan
clear
This is the image for the news article titled  Ground Broken on Services Facility
Ground Broken on Services Facility
12/16/2016
CKSD keeps its promise to build a new facility to consolidate services.
Read More About Ground Broken on Services Facility
clear
This is the image for the news article titled See What the New CK Campus Will Look Like
See What the New CK Campus Will Look Like
12/02/2016
Families and community are invited to ask questions Dec. 6.
Read More About See What the New CK Campus Will Look Like
clear
This is the image for the news article titled Join Us Dec. 6!
Join Us Dec. 6!
11/21/2016
See designs for the new CK Middle and CK High. Tell us what you think!
Read More About Join Us Dec. 6!
clear
This is the image for the news article titled Ribbon Is Cut at Silverdale Elementary
Ribbon Is Cut at Silverdale Elementary
11/04/2016
Students celebrated their new school with a ribbon cutting.
Read More About Ribbon Is Cut at Silverdale Elementary
clear
Crews installed doors on classrooms throughout PineCrest.
clear
 Commons area
Want a Sneak Peek of Oly’s Remodel?
09/29/2016
Central Kitsap School Board approves first phase of design work.
Read More About Want a Sneak Peek of Oly’s Remodel?
clear
This is the image for the news article titled Teachers Move in to Remodeled Silverdale Elementary
Teachers Move in to Remodeled Silverdale Elementary
08/24/2016
School staff have been hard at work readying the building for students.
Read More About Teachers Move in to Remodeled Silverdale Elementary
clear
This is the image for the news article titled Summer Work Spruces Up Klahowya
Summer Work Spruces Up Klahowya
08/12/2016
New classrooms, new roof and other work is just the start of improvements at Klahowya.
Read More About Summer Work Spruces Up Klahowya
clear
This is the image for the news article titled Fresh Tracks Coming to Fairview, Ridgetop
clear
Community members talk about school history with architects
Going from Wrong to Right in New CK School Designs
07/01/2016
Architects wrap up an information-gathering phase before sketching layouts for the new schools.
Read More About Going from Wrong to Right in New CK School Designs
clear
This is the image for the news article titled Board Approves Next Steps for Klahowya Addition
Board Approves Next Steps for Klahowya Addition
06/22/2016
Board members considered and voted on initial sketches and floor plans.
Read More About Board Approves Next Steps for Klahowya Addition
clear
Science Kit Center
Construction Preparation Underway
06/09/2016
The district is preparing for four major construction projects.
Read More About Construction Preparation Underway
clear
This is the image for the news article titled Klahowya Project Reaches Milestone
clear
Students Wield Pens for Future of CK Campus
Students Wield Pens for Future of CK Campus
05/16/2016
Workshops and staff meetings guide design for new schools.
Read More About Students Wield Pens for Future of CK Campus
clear
This is the image for the news article titled Klahowya Designs on the Move
Klahowya Designs on the Move
05/13/2016
The design process is moving quickly for the addition at Klahowya Secondary.
Read More About Klahowya Designs on the Move
clear
Bond Dollars Going to Work
Bond Dollars Going to Work
05/12/2016
Design work has begun on big projects and repairs at three schools starts this summer.
Read More About Bond Dollars Going to Work
clear
Illustration of facility
Designs Progress for Support Services Building
04/08/2016
Once built, Transportation, Food Services and Warehouse departments will move to the new facility.
Read More About Designs Progress for Support Services Building
clear
Staff and students at one school reimagine their existing and future spaces.
Outside Thinking Inside the Box
03/31/2016
Staff and students at one school reimagine their existing and future spaces.
Read More About Outside Thinking Inside the Box
clear
Thank You Central Kitsap Community!
Thank You Central Kitsap Community!
02/22/2016
The passage of a bond and levy measure for our schools has been certified.
Read More About Thank You Central Kitsap Community!
clear
Revenue and Expenditures
Levy Projects Balance Report
12/29/2015
Three years into the levy, we have made significant progress on promised projects.
Read More About Levy Projects Balance Report
clear
This is the image for the news article titled Progress Visible at Silverdale Elementary
Progress Visible at Silverdale Elementary
12/28/2015
The renovation and modernization project is on time and on budget with the school set to reopen in fall 2016.
Read More About Progress Visible at Silverdale Elementary
clear
This is the image for the news article titled Hawk Elementary Students Christen New Playfield
Hawk Elementary Students Christen New Playfield
09/16/2015
If smiles are an indication, Hawk Elementary at Jackson Park students believe their new playfield was worth the wait.
Read More About Hawk Elementary Students Christen New Playfield
clear
This is the image for the news article titled Renovation Work Progressing Quickly
Renovation Work Progressing Quickly
08/03/2015
If you've gone past Silverdale Elementary lately, you may not recognize it.
Read More About Renovation Work Progressing Quickly
clear
This is the image for the news article titled Another promise kept
Another promise kept
06/20/2015
On their last day of school, students at Silverdale Elementary celebrated more than just the end of a school year. They also took some time to celebrate the start of something.
Read More About Another promise kept
clear
This is the image for the news article titled Silverdale Elementary Staff Pack Up for Temporary Move
Silverdale Elementary Staff Pack Up for Temporary Move
06/18/2015
A week after school let out, staff and moving crews boxed up everything inside Silverdale Elementary.
Read More About Silverdale Elementary Staff Pack Up for Temporary Move
clear
Local leaders Officially Open Hawk Elementary
Shaping Schools for Years to Come
01/05/2015
Students and community leaders hailed the opening of John D. "Bud Hawk Elementary at Jackson Park in September 2014. The school's construction was the largest project we promised when Central Kitsap voters approved the 2011 capital projects levy.
Read More About Shaping Schools for Years to Come
clear
This is the image for the news article titled Jackson Park Elementary School Takes Shape!
Jackson Park Elementary School Takes Shape!
07/08/2014
The district broke ground on the project in June. Since then, students have been watching the new school take shape right before their eyes.
Read More About Jackson Park Elementary School Takes Shape!
clear
This is the image for the news article titled 2011 Capital Projects Measure Update for 2013
2011 Capital Projects Measure Update for 2013
07/07/2014
The first two years of the levy are behind us—and we’ve made great progress!
Read More About 2011 Capital Projects Measure Update for 2013
clear
Artist's rendering for the new jackson Park
District to Break Ground on New Jackson Park
05/20/2013
Central Kitsap School District is scheduled to break ground in May on the long-awaited replacement building for Jackson Park Elementary School.
Read More About District to Break Ground on New Jackson Park
clear
This is the image for the news article titled 2012 Capital Levy Projects Progress
2012 Capital Levy Projects Progress
05/19/2013
We’re making progress already! As work continues, we will provide a clear and detailed picture of our revenue and expenditures.
Read More About 2012 Capital Levy Projects Progress
clear