CK High
Status: We hosted a grand opening for our community on October 2. The satellite gym is finished. We are sharing student feedback cards with the design and construction teams.
What’s Next: Crews will finish painting and other interior work on the satellite gym (the former CK Middle gym) and install bleachers at the new softball field.
Klahowya Secondary
Status: Athletics sponsor Integrity Roofing & Construction has begun adding attachment metal for the roofing on the grandstands. They are awaiting arrival of the roofing material.
What’s Next: Integrity Roofing hopes to complete the roof before the final home football game on November 8.
CK Admin/Silverdale Library
Status: The demolition contractor took over the old CKHS site; the abatement process will begin on October 31. Creation of construction documents for Building 900 has begun.
What’s Next: We will seek construction bids in early 2020, with construction expected to begin that spring
Seabeck
Status: The demolition contractor has begun the abatement process.
What’s Next: Demolition of the old portions of the school will occur following abatement. The newest portion, the gymnasium, will be preserved and available for community use.