Capital Projects Update: March 2018
Capital Projects Update: March 2018
Posted on 03/15/2018
CK Campus from above.

We’ve started the next major phase of our efforts to secure access to our schools. Construction crews are now at Silver Ridge, and are preparing for work at Ridgetop and Emerald Heights. We expect to secure entrances at all schools by the end of the next school year.

Click on any of the images below for updates on a specific project.

Safety & Security 

silver ridge entrance

Status: Construction crews are at Silver Ridge. They’ve demolished the main office and are rebuilding the entrance to make it more secure.

What's Next: Crews are planning for construction at Emerald Heights and Ridgetop.

Olympic High School

OHS future performing arts center

Status: Concrete floors are being poured on the second floor of the new core. Siding is up on the new manufacturing lab.

What's Next: Crews will install a pedestrian bridge near the classroom wing.

CK High & Middle

Aerial view of the CK Campus

Status: Framing work has begun on the high school portion of the building, and the high school gym is going up. Upper level floors are being poured in the middle school.

What's Next: Steel erection will continue into the high school area.

Klahowya Secondary

Staff moving in to a new classroom
Status: Three new classrooms opened: family and consumer science, fitness and science.

What's Next: Crews will continue framing, work on the gym and classroom wing and site work.