CK High & Middle
Status: Work on the exterior of the schools is nearly done. Drywall installation and painting are going on throughout the building. Gym floors in CK Middle are done, and flooring is being laid in CK High.
What’s next: Work will continue on the baseball field. CK Middle classrooms will look more finished as we prepare to install furniture and technology hardware. We're on track to start classes on April 8.
Olympic High
Status: The final phase of the school addition and modernization project is nearly complete. This week, staff began moving in to the library, main office, student store and several classrooms.
What’s next: We celebrate! The Grand Opening Celebration is at 6:30 p.m., Thursday, Jan. 24.
Silverdale Elementary
Complete! Classes have started in the new wing at Silverdale. This bright and beautiful addition, called “Sky Pod,” includes five classrooms, a small common space and bathrooms.